HomeLocal NewsLagos Marine bridge rehabilitation 66% completed

Lagos Marine bridge rehabilitation 66% completed

Date:

Related stories

NDLEA arrests 230 suspects in major drug crackdown across Kano

The National Drug Law Enforcement Agency (NDLEA) has arrested...

Gov Yusuf presents N1.36trn 2026 budget

Kano State Governor, Alhaji Abba Kabir Yusuf, has presented...

Gov Yusuf appoints 400 mathematics teachers to boost education in Kano

Kano State Governor, Alhaji Abba Kabir Yusuf, has presented...

Gov Yusuf deploys 1,600 watchmen to boost security in secondary schools

Kano State Governor, Alhaji Abba Kabir Yusuf, has rolled...

Kano govt calls for strict ethics in AI-driven journalism

The Kano State Government has called on online journalists...
spot_img

The Federal Controller of Works in Lagos State, Mr Olukayode Popoola, on Saturday says the ongoing rehabilitation of the Marine Bridge in Apapa is 66 per cent completed.

Popoola, in an interview with  the News Agency of Nigeria (NAN) in Lagos, said that rehabilitation of the bridge was being done in phases.

The controller said that 24 expansion joints and 120 bearings had been replaced in previous phases.

READ ALSO: Kaduna Varsity gets new Vice-Chancellor

He said in the new phase of rehabilitation works that began on Monday, 40 additional bearings and six expansion joints were being replaced.

“For this particular section that we just closed, we are going to replace 40 bearings and six numbers expansion joints.

“Previously, we have changed 120 bearings and 24 number expansion joints. The repair is a carryover from last year.

“The contract was awarded in September 2019, and the contractor started work in October, 2019 with the rehabilitation of failed sections of the bridge.

“The contractor has achieved 66.19 per cent completion and so far.

“Repair works have been carried out on two sections of the bridge with the replacement of 120 bearings, 24 expansion joints and the resurfacing of 610m of asphalt.

“The partial closure of the bridge on Monday is to allow the contractor rehabilitate the damaged section, which will involve the replacement of 40 bearings and six number expansion joints,’’ he said.

Popoola explained that the repair works in the new phase  would be completed by  April 2022.

He appealed to motorists to obey traffic regulations around the construction zone where traffic was partially diverted to avert gridlock.

A NAN correspondent who visited the construction site observed that lifting towers placed on Self Propelled Modular Trailers (SPMT) were being used to jerk up two sections of a bridge deck.

Construction workers were seen climbing through the lifting towers to work simultaneously under the bridge deck and its top surface on the Ijora bound carriageway. (NAN)